Sewer construction update
Banner Daily Update posted Mon. June 25
Fritz Way & Conant Street Crew #1
June 25-28 Installing sewer pipe in Fritz Way and Conant Street from Brown Street toward Bradford Street. Temporary traffic detours should be expected in Fritz Way and Conant Street Areas.
Shank Painter Road Crew #2
June 25-27 Install sewer pipe from Brown Street to Bradford Street. One lane of traffic will be open in this area of Shank Painter Road.
Shank Painter Road Crew #3
June 26-28 Paving of Shank Painter Road from Province Road to Bradford Street. One lane of traffic will be open in this area of Shank Painter road.
Brown Street Crew #4
June 27-28 Paving of Brown Street from Shank Painter Road to Pleasant Street. Temporary detours and one lane traffic should be expected on Brown Street.
Sewer construction schedule is subject to change. Seek alternative routes if possible. Any questions or concerns should be directed to the Ron Gamella at the Department of Public Works (508) 487-7060.
|