Sewer Construction Update
Banner Daily Update posted Fri. Oct. 19
The following is the anticipated schedule of the Phase 2 and Manor Area sewer construction work to be performed for the upcoming weeks.
Snow’s Lane and Race Road - Crew #1
Oct. 17-24 Install sewer pipe on Snow’s Ln. up to #10 Snows Ln. Temporary road closures and parking bans should be expected on Snow’s Ln.
Conant Street, and Montello Street - Crew #2
Oct. 12-17 Install sewer pipe on Conant St. from Bradford St. toward Commercial St. up to house # 11 Conant St. Temporary traffic detours and parking bans should be expected on this section of Conant St.
Oct. 17-22 Install sewer pipe on Montello St. from Bradford St. toward Commercial St. up to house #6 Montello St. Temporary traffic detours and parking bans should be expected on this section of Montello St.
Oct. 19 Install sewer pipe on Brown St. from Shank Painter Rd. up to house #2 Brown St. adjacent to fire station. Temporary traffic detours and parking bans should be expected on this section of Brown St.
Central Street, Atlantic Avenue, and Conant St. – Crew #3
Oct. 17-19 Install sewer service connections on Central St. Temporary traffic detours and parking bans should be expected on Central St.
Oct. 17-22 Install sewer service connections on Atlantic Ave. Temporary traffic detours and parking bans should be expected on Atlantic Ave.
Oct. 19-24 Install sewer service connections on Conant St. Temporary traffic detours and parking bans should be expected on Conant St.
Grace Gouveia Building Parking Lot, 26 Alden St. – Crew #4
Oct. 18-26 Site work will continue in the parking lot area adjacent to the Grace Gouveia Building on Alden St.
Shank Painter Road Pump Station – Crew #5
Oct. 12-26 Work will continue in the parking lot area adjacent to the fire station on Shank Painter Rd.
Paving – Crew #5
Bradford Street, Prince Street, Cemetery Road, and Standish Street
Oct. 17, Oct. 24 and Oct. 25 Crews will be paving in various location on the streets listed above.
Sewer construction schedule is subject to change. Seek alternative routes if possible. Any questions or concerns should be directed to Ron Gamella at Department of Public Works 508-487-7060.
|
Commercial Street repave hits the skids Medflight transports Truro man Rice to head Payomet Who Killed the Electric Car? Thousands flock to shellfish fest
|
 |
 |
 |




 |