Sewer construction update
Shank Painter/Rt. 6/Brown Street Crew #1
June 11—12 Finish sewer pipe installation on Shank Painter Road.
June 13—22 Install sewer pipe in Brown Street from Shank Painter Road to Pleasant Street. Brown Street will be closed to through traffic.
Shank Painter Road Crew #2
June 11 Begin dewatering at Fire Station parking lot on Shank Painter Road.
June 11—22 Install sewer pipe on Shank Painter Road from Brown Street toward Bradford Street.
Winthrop Street and Court Street - Directional Drilling of Sewer Pipe
June 11—15 Set up and perform directional drilling affecting Winthrop Street at the Fire Station parking lot and Court Street at No. 33 Court Street. A section of Court Street will be closed to through traffic at times during this installation.
June 13 Court Street will be closed from Shank Painter Road to Watson’s Court. Homeowners and business will have access to their property. No through traffic.
Franklin St/Pleasant St/Kings Way & Montello St.
June 13 Due to the necessary test hole excavation in Franklin St/Pleasant St and Kings Way these street my be temporally closed. Detour signs will provide alternate routes.
Sewer construction schedule is subject to change. Seek alternative routes if possible. Any questions or concerns should be directed to the Ron Gamella at the Department of Public Works (508) 487-7060.
|