Sewer construction update
Updated July 16
The following is the anticipated schedule of the Phase 2 sewer construction work to be performed for the upcoming week.
Pleasant Street - Crew #1
July 16-20 Install sewer pipe on Pleasant St. from Brown St. toward Bradford St. Temporary traffic detours should be expected in the Pleasant St. area.
Conant St., Montello St. & Pleasant St - Crew #2
July 16-20 Install sewer stubs for properties to be connected on Conant St., Montello St., and Pleasant St. Temporary traffic detours should be expected in these areas.
Court Street - Crew #3
July 16-20 Install sewer pipe on Court Street from #33 Court St. toward Shank Painter Rd. Temporary traffic detours should be expected in the Court St. area.
Shank Painter Road - Crew #4
July 18 Install pavement top course on Shank Painter Rd. from Brown St. toward Bradford St. One lane of traffic should be expected in some areas along Shank Painter Road.
Shank Painter Road Pump Station – Crew #5
July 16-20 Work will continue in the parking lot area adjacent to the fire station on Shank Painter Road.
Sewer construction schedule is subject to change. Seek alternative routes if possible. Any questions or concerns should be directed to Ron Gamella at Department of Public Works 508-487-7060.
|