Sewer construction update
Updated July 23
The following is the anticipated schedule of the Phase 2 sewer construction work to be performed for the upcoming week.
Pleasant Street - Crew #1
July 23-27 — Install sewer pipe on Pleasant St. from Race Rd. toward Bradford St. Temporary traffic detours should be expected in the Pleasant St. area.
Pleasant Street - Crew #2
July 23-27 — Install sewer stubs for properties to be connected on Pleasant St. Temporary traffic detours should be expected in the Pleasant St. area.
Court Street - Crew #3
July 23-25 — Install sewer pipe on Court Street from #41 Court St. toward Shank Painter Rd. Temporary traffic detours should be expected in the Court St. area.
July 26-27 — Install sewer pipe on Winthrop St. from Court St. toward Brown St. Temporary traffic detours should be expected in this area of Winthrop St.
Shank Painter Road Pump Station – Crew #4
July 23-27 — Work will continue in the parking lot area adjacent to the fire station on Shank Painter Road.
Sewer construction schedule is subject to change. Seek alternative routes if possible. Any questions or concerns should be directed to Ron Gamella at Department of Public Works 508-487-7060.
|