Sewer construction update
Updated July 27
The following is the anticipated schedule of the Phase 2 sewer construction work to be performed for the upcoming week.
Race Road and Franklin Street - Crew #1
July 26-27 Install sewer pipe on Race Rd. toward Franklin St. Temporary traffic detours should be expected in the Race Rd. and Franklin St. areas.
July 30-Aug.3 Install sewer pipe on Franklin St. from Race Rd. toward West Franklin St. Temporary traffic detours should be expected in the Franklin St. area.
Court Street and Winthrop Street- Crew #2
July 26-27 Install sewer pipe on Winthrop St. from Court St. to Brown St. Temporary traffic detours of this section of Winthrop St. should be expected.
July 30-Aug. 3 Install sewer pipe on Court St. from # 33 Court St. to intersection of Court St. and Holway Ave. Temporary traffic detours should be expected in this area of Court St.
Winthrop Street - Crew #3
July 26-27 Install sewer stubs for properties to be connected on Winthrop St. between Court St. and Brown St. Temporary traffic detours in this section of Winthrop St. should be expected
Shank Painter Road Pump Station – Crew #4
July 26-Aug.3 Work will continue in the parking lot area adjacent to the fire station on Shank Painter Road.
Sewer construction schedule is subject to change. Seek alternative routes if possible. Any questions or concerns should be directed to Ron Gamella at Department of Public Works 508-487-7060.
|