Provincetown Sewer Construction Update
The following is the anticipated schedule of the Phase 2 sewer construction work to be performed for the upcoming week.
Franklin Street - Crew #1
August 6-10 Install sewer pipe on Franklin St. from Race Rd. toward Creek Rd. Temporary traffic detours should be expected in the Franklin St. area.
Court Street and Holway Avenue - Crew #2
August 6-10 Install sewer pipe on Holway Ave. from Court St. to end of Holway Ave. Temporary traffic detours and parking bans should be expected in this section of Court St. and Holway Ave.
Shank Painter Road Pump Station – Crew #3
August 6-10 Work will continue in the parking lot area adjacent to the fire station on Shank Painter Road.
Street Paving - Crew #4
August 8-9 Paving will be conducted on the following streets: Brown St., Fritz Way, Conant St., Montello St., Pleasant St., Race Rd., Winthrop St., and Court St. Temporary traffic detours and parking bans should be expected in these areas.
Sewer construction schedule is subject to change. Seek alternative routes if possible. Any questions or concerns should be directed to Ron Gamella at Department of Public Works 508-487-7060.
|
The lottery labyrinth Dermo weakens shellfish market A continuing inspiration Outer Cape Worship Services For Your Information
|
 |
 |
 |





 |