Sewer Construction Update
Banner Daily Update posted Sat. Sept. 22
The following is the anticipated schedule of the Phase 2 and Manor Area sewer construction work to be performed for the upcoming weeks.
Pleasant Street Ext., Snow’s Lane and Carnes Lane- Crew #1
Sept. 25—Oct. 5 Install sewer pipe on Pleasant St. Ext. and Snow’s Ln. Temporary traffic detours and parking bans should be expected on Pleasant St. Ext.
Sept. 25—Oct. 5 Install sewer pipe on Carnes Ln. from Race Rd. to #15 Carnes Ln. Temporary road closures and parking bans should be expected on Carnes Ln.
Bradford Street (East) and Montello St.- Crew #2
Sept. 25—28 Install sewer pipe on Bradford St. from Shank Painter Rd. toward the east side of Bradford St. Temporary traffic detours, road closures, and parking bans should be expected in sections of Bradford St.
Sept. 28—Oct. 3 Install sewer pipe on Montello St. from Bradford St. toward Commercial St. up to #6 Montello St. Temporary traffic detours and parking bans should be expected on this section of Montello St.
Cemetery Road, Alden Street, and Manor Pump Station - Crew #3
Sept. 25—26 Install sewer pipe on Cemetery Rd. toward Wareham St. Temporary traffic detours and road closures should be expected in this area Cemetery Rd.
Sept. 26—28 Install sewer pipe on Alden St. in front of Grace Gouveia building. Temporary traffic detours and road closures should be expected in this area of Alden St.
Sept. 28—Oct. 5 Install sewer pipe on Standish St. from Cemetery Rd. to #21 Standish St. Temporary traffic detours and road closures should be expected in this area of Standish St.
Shank Painter Road Pump Station – Crew #4
Sept. 25—Oct. 5 Work will continue in the parking lot area adjacent to the fire station on Shank Painter Rd.
Paving – Crew #5
Court Street, Holway Ave, Prince Street, Mozart Avenue, Cudworth Street, and Bradford Street
Sept. 27—Oct.2 Crew will be paving in various location on the above listed streets. Temporary traffic detours and parking bans should be expected in these areas.
Sewer construction schedule is subject to change. Seek alternative routes if possible. Any questions or concerns should be directed to Ron Gamella at Department of Public Works 508-487-7060.
|