Provincetown sewer contruction update
Banner Daily Update posted Thurs. Oct. 5
The following is the anticipated schedule of the Phase 2 and Manor Area sewer construction work to be performed for the upcoming weeks.
Carnes Lane, Snow’s Lane, and Montello Street - Crew #1
Oct.9-12 Install sewer pipe on Carnes Ln. from Race Rd. up to #15 Carnes Ln. Temporary road closures and parking bans should be expected on Carnes Ln.
Oct. 10-16 Install sewer pipe on Snow’s Ln. up to #10 Snows Ln. Temporary road closures and parking bans should be expected on Snow’s Ln.
Oct. 12-19 Install sewer pipe on Montello St. from Bradford St. toward Commercial St. up to house # 6 Montello St. Temporary traffic detours and parking bans should be expected on this section of Montello St.
Central Street, Atlantic Avenue, and Conant Street - Crew #2
Oct.5-15 Install sewer pipe on Central St. toward Commercial St. Temporary traffic detours and parking bans should be expected on this section of Central St.
Oct. 12-17 Install sewer pipe on Atlantic Ave. from Bradford St. toward Commercial St. up to house # 9 Atlantic Ave. Temporary traffic detours and parking bans should be expected on this section of Atlantic Ave.
Oct. 16-19 Install sewer pipe on Conant St. from Bradford St. toward Commercial St. up to house # 11 Conant St. Temporary traffic detours and parking bans should be expected on this section of Conant St.
Shank Painter Road Pump Station – Crew #3
Oct. 9-19 Work will continue in the parking lot area adjacent to the fire station on Shank Painter Rd.
Sewer construction schedule is subject to change. Seek alternative routes if possible. Any questions or concerns should be directed to Ron Gamella at Department of Public Works 508-487-7060.
|