Sewer Construction Update
The following is the anticipated schedule of the Phase 2 and Manor Area sewer construction work to be performed for the upcoming weeks.
Alden Street, Franklin Street, and Pleasant Street Extension - Crew #1
November 7th – November 12th Work will be performed in various manholes along Alden St. Temporary areas of one lane traffic should be expected on Alden St.
November 13th – November 26th Install sewer pipe on Franklin St. between Race Rd. and Creek Rd. Temporary road closures and parking bans should be expected on this section of Franklin St.
November 21st – November 30th Install sewer service connections and storm drain pipe on Pleasant St. Ext. from Snow’s Ln. to Brown St. Temporary road closures and parking bans should be expected on this section of Pleasant St. Ext.
Atlantic Avenue and Commercial Street - Crew #2
November 8th – November 14th Install sewer pipe and structures on Atlantic Ave. and Commercial St. from house # 3 Atlantic Ave. to house #160 Commercial St. Temporary traffic detours and parking bans should be expected on this section of Atlantic Ave. and Commercial St.
Pleasant Street, Route 6, and Winthrop Street – Crew #3
November 7th – November 9th Install sewer pipe on Pleasant St. from house #11 Pleasant St. toward Commercial St. Temporary traffic detours and parking bans should be expected on this section of Pleasant St.
November 9th – November 12th Install sewer force main connection on Route 6 in the vicinity of the wastewater treatment plant. Work will be performed on the shoulder of Route 6 in this location.
November 12th – November 15th Install sewer pipe and structures on Winthrop St. between house #1 and #3 Winthrop St. Temporary traffic detours and parking bans should be expected on this section of Winthrop St.
Grace Gouveia Building Parking Lot and Manor Pump Station, 26 Alden Street – Crew #4
November 7th – November 16th Site work will continue in the parking lot area and pump station adjacent to the Grace Gouveia Building on Alden St.
Shank Painter Road Pump Station – Crew #5
November 7th – November 30th Work will continue in the parking lot area adjacent to the fire station on Shank Painter Rd.
Paving – Atlantic Avenue, Conant Street, Montello Street, Alden Street, Court Street Crew 5
November 8th, 14th and 15th Crews will be paving streets at various locations on the above listed streets
Sewer construction schedule is subject to change. Seek alternative routes if possible. Any questions or concerns should be directed to Ron Gamella at Department of Public Works 508-487-7060.
|