Sewer Construction Update
Banner Daily Update Fri. Nov. 16
The following is the anticipated schedule of the Phase 2 and Manor Area sewer construction work to be performed for the upcoming weeks.
Alden Street, Franklin Street, and Pleasant Street Extension - Crew #1
Nov. 19th – Nov. 26th Install sewer pipe on Franklin St. between Race Rd. and Creek Rd. Temporary road closures and parking bans should be expected on this section of Franklin St.
Nov. 21st – Nov. 30th Install sewer service connections and storm drain pipe on Pleasant St. Ext. from Snow’s Ln. to Brown St. Temporary road closures and parking bans should be expected on this section of Pleasant St. Ext.
Atlantic Avenue and Commercial Street - Crew #2
Nov. 19th – Nov. 30th Install sewer pipe on Winthrop St. from fire station toward Bradford St. Temporary traffic detours and parking bans should be expected on this section of Atlantic Ave. and Commercial St.
Pleasant Street, Route 6, and Winthrop Street – Crew #3
Nov. 19th – Nov. 20th Install sewer force main connection on Route 6 in the vicinity of the wastewater treatment plant. Work will be performed on the shoulder of Route 6 in this location.
Nov. 19th – Nov. 20th Install sewer pipe and structures on Winthrop St. between house #1 and #3 Winthrop St. Temporary traffic detours and parking bans should be expected on this section of Winthrop St.
Grace Gouveia Building Parking Lot and Manor Pump Station, 26 Alden Street – Crew #4
Nov. 19th – Nov. 30th Site work will continue in the parking lot area and pump station adjacent to the Grace Gouveia Building on Alden St.
Shank Painter Road Pump Station – Crew #5
Nov. 19th – Nov. 30th Work will continue in the parking lot area adjacent to the fire station on Shank Painter Rd.
Paving – Atlantic Avenue, Conant Street, Montello Street, Alden Street, Court Street – Crew #5
Nov. 8th, 14th and 15th Crews will be paving streets at various locations on the above listed streets.
Sewer construction schedule is subject to change. Seek alternative routes if possible. Any questions or concerns should be directed to Ron Gamella at Department of Public Works 508-487-7060.
|